摘要 笔者通过对几例大型变压器中性点绝缘故障实例的分析,说明了现场考核变压器中性点绝缘的必要性。文章还介绍了利用变压器中性点现场交流耐压试验以考核其绝缘的方法,并提出对变压器中性点进行局部放电测量的建议。 Through the analysis of some neutral-point insulation faults of large transformers, the necessity of on-site examination on neutral-point insulation of large transformers is discussed. The method of assessing neutral-point insulation of a large transformer through on-site AC voltage-endurance test is presented. Moreover, partial discharge measurement of neutral point of transformer is suggested.
出处 《高压电器》 CAS CSCD 北大核心 2009年第2期114-116,共3页 High Voltage Apparatus
关键词 变压器 中性点绝缘 现场考核 交流耐压试验 局部放电测量 transformer neutral-point insulation on-site examination AC voltage-endurance test partial discharge measurement
  • 相关文献

参考文献3

  • 1GB50150-2006,电气装置安装工程电气设备交接试验标准[S]
  • 2GB1094.3-2003.电力变压器第3部分:绝缘水平、绝缘试验和外绝缘空气间隙[S].[S].,..
  • 3DL/T596-1996.电力设备预防性试验规程[S].[S].,..