摘要 阐述了湖州垃圾焚烧发电工程主厂房的结构方案选择、计算软件应用、垃圾储存池设计、混凝土结构超长无缝施工技术、地基基础设计等问题,论述了垃圾焚烧发电厂主厂房结构的特点及设计要点。 Design of Huzhou power project by incinerating refuse, such as the selection of structural scheme for the main plant, use of the structure calculation software, design of refuse bunker, non-joint construction technique as to the over-length concrete structure, subsoil treatment and foundation design, is introduced and expounded. The features and essentials of structural design in the main plant are discussed by illustrating its specific engineer design.
出处 《建筑结构》 CSCD 北大核心 2009年第3期69-71,共3页 Building Structure
关键词 垃圾焚烧发电厂 垃圾储存池 超长无缝施工技术 SATWE power plant by incinerating refuse refuse bunker over-length and non-joint construction technique SATWE
  • 相关文献

参考文献4

  • 1.GB50010-2002混凝土结构设计规范[S].北京:中国建筑工业出版社,2002..
  • 2.GB50011-2001建筑抗震设计规范[S].北京:中国建筑工业出版社,2001..
  • 3.GB50017-2003钢结构设计规范[S].北京:中国计划出版社,2003..
  • 4曾华荣.破碎带地基基础分析处理[J].西部探矿工程,1997,9(6):29-30. 被引量:2

共引文献1457

同被引文献19

引证文献6

二级引证文献8

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部