注浆与疏干在斜井防治水中的应用 被引量:2

Application of Grouting and Dewatering to Water Control in Inclined Shaft
下载PDF
导出
摘要 在高峰锡矿探采斜井的建设中,采用了分段工作面水泥预注浆的方法防止涌水,但一些不能进浆的细小裂隙的残余涌水仍严重妨碍着掘进施工。为避免溶洞、断裂带等大开度空隙的涌水,减少细裂隙的残余涌水量,将工作面水泥预注浆与井内水平孔疏干联合应用,达到了加快掘进速度,节省治水工程投资的目的。 n the construction of a inclined exploratory and extraction shift in Gaofeng Tin Mine,a sectional cement pregrouting method was used to prevent the groundwater gush,but the residual water pouring from some fine fissures in which cement grout can′t penetrate still hindered the construction of the shift seriously in order to avoide heavy water pouring from lagre openings such as caverns and faults and reduce the amount of residual water from fine fissures,cement pregrouting at work face was jointly used in combination with horizontal hole dewatering in the shift,resulting in speeding up the excavation of the shift and saving investment cost for water control project.
作者 郑长成
机构地区 长沙矿山研究院
出处 《矿业研究与开发》 CAS 1998年第2期12-15,共4页 Mining Research and Development
关键词 注浆 疏干 斜井 防水 治水 矿井水 routing,Dewatering,Inclined shift,Water control
  • 相关文献

参考文献4

  • 1Ewert F K. The individual groutability of rocks.Water Power & Dam Construction,January 1992.
  • 2Crawford A M et al. Groutability ratio for filter blocking of joints in rock. Proc of the 25th Symposium on Rock Mechanies, 1984.
  • 3Houlsby A C. Cement grouting for dams. proc. Conf. on Grouting in Geotechnical Engineering, ASCE, New Orleans,1982.
  • 4Milanovic p T. Karst Hydrogeology. Water Resources Publications, 1981.

同被引文献7

引证文献2

二级引证文献14

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部