摘要
详细介绍了国电小龙潭发电厂410 t/h锅炉的烟气脱硫除尘技改工程的工艺原理、系统流程、主要设备等,并结合系统调试过程中出现的问题,对该工艺的运行调试进行了评述。
The technology principle, system process flow and main equipments of 410 t/h boiler flue gas desulphurization and dedust technical reformation project were presented in detail. Combining with the problems occurred in system commission process, the operation and commission of this technology were reviewed.
出处
《华电技术》
CAS
2009年第4期72-74,77,共4页
HUADIAN TECHNOLOGY
关键词
循环流化床锅炉
脱硫
电除尘器
改造
circulating fluidized bed boiler
desulphurization
electro-static precipitator
reformation