摘要
本文用系统分析的思想。对玄武湖水底交通隧道的两种施工方案(明挖法与盾构法)进行了比选,并对明挖法方案进行了优化,最后确定了最佳方案——箱涵顶进加筑堤开槽埋管方法。
Based on the thought of systematic engineering analysis,two working schemes(opencut and cover method,shield method) of Xuanwu Lake Subaqueous Highway Tunnel are contrasted and evaluated in this paper.The opencut and cover method is optimized by the authors.According to this paper,the optimum scheme is the dike construction and pipe burial method with box culvert jacking techniques.
出处
《水文地质工程地质》
CAS
CSCD
1998年第2期16-18,37,共4页
Hydrogeology & Engineering Geology
关键词
水底交通隧道
系统工程
湖泊
比选优化
施工方案
subaqueous highway tunnel,systems engineering, Xuanwu Lake,shield method,opencut and cover method,contrast and optimization,box culvert jacking