摘要
以吕梁汾阳220 kV变电站于2007年11月进行了综合自动化改造为例,监控系统为国电南京自动化股份有限公司(以下简称"南自")生产的PS6000变电站监控系统,阐述了改造后不久,出现了远动通讯(和中调、地调的通讯)频繁中断的问题,为此保护人员与南自研发人员对装置的运行环境、运行状况进行现场的多次模拟试验,问题最终得到了很好的解决。
Taking Lvliang Fenyang 220 kV substation comprehensive transformation of automation, control systems for the country' s production of electricity from South PS6000 substation monitoring system in November, 2007 as an example, the phenomenon that GM shortly after the emergence of remote communications, in tune, and to the tune of communication have frequent disruptions is introduced, for which the protection personnel and research staff from the South to the device' s operating environment, operation of a number of on-site simulation tests are proposed. Suggestions to solve the problems are put forward.
出处
《山西电力》
2009年第2期30-31,共2页
Shanxi Electric Power
关键词
远动通讯中断
问题分析
处理过程
remote communication interruption
problem analysis
processes