简支转连续梁桥的合理施工体系转换 被引量:5

Conversion of Reasonable Construction System for Continuous Beam Turned from Simple Beam
下载PDF
导出
摘要 从现浇段浇注顺序、后连续预应力筋的张拉顺序和临时支座的拆除顺序三方面研究了简支转连续施工体系的合理工序,从受力角度对不同施工工序进行对比分析,建议现浇浇筑和张拉的合理工序为隔端浇筑、隔端张拉,临时支座拆除的合理工序为"对称拆除"。 The conversion of optimal construction system is studied in terms of the pouring order of cast-in-site segment, tensioning of continuous tendon and dismantling of temporary bearing. Different construction procedures are analyzed from the perspective of force. It is considered that the optimal procedure for pouring of cast-in-site segment and tensioning is interval pouring or interval tensioning, and the optimal procedure for dismantling of temporary bearing is symmetrical dismantling.
出处 《东北林业大学学报》 CAS CSCD 北大核心 2009年第4期96-97,101,共3页 Journal of Northeast Forestry University
关键词 先简支后连续梁 体系转换 支座 Continuous beam turned from simple beam System conversion Bearing
  • 相关文献

参考文献5

二级参考文献9

共引文献40

同被引文献21

引证文献5

二级引证文献14

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部