The towers of CCTV main building have directional incline, and one M1280D and one M600D whip-typed tower crane for No. 1 and No. 2 tower are installed separately, which are difficult to be disassembled, so two M600D tower cranes need to be installed to cantilever position. The cantilever support design -and attachment design and processing for M600D tower crane are described in detail. It is pointed out that adding column for truss can strength the cantilever, and adding attached bar can reduce unfavorable load of tower crane to cantilever truss. Furthermore, the displacement installation process for M600D tower crane in cantilever position is introduced.