地铁工程风险评价——以南京地铁2号线为例 被引量:14

Risk Assessment for Subway Projects:Taking Nanjing Subway Line 2 as an Example
原文传递
导出
摘要 通过问卷调查,从总体和施工角度分层次识别了南京地铁2号线的风险因素,又应用模糊层次分析法对风险因素进行了评价。评价结果表明,规划阶段和设计阶段的风险因素列于总体风险评价的前列,而质量风险和地质风险则高居施工阶段的前列。风险的识别和评价是风险管理的重要手段,本文的评价结果不仅有助于识别南京地铁2号线的重要风险并进行有效应对,而且对其它筹建地铁工程的风险管理有一定借鉴作用。 This paper identified risk factors which Nanjing subway line 2 might encounter with by using questionnaire survey firstly. Risk factors were classified into 5 categories systematically with construction stage further being divided into another 5 sub-categories. The risks then were assessed using fuzzy Analytic Hierarchy Process (AHP). The assessment results showed risks in planning and designing stage ranked high in holistic level while geological and quality risks in sublevel of construction stage. This assessment results are expected not only to be helpful for managers of Nanjing subway line 2 to respond to important risks effectively, but also beneficial for other subway projects which are to be built.
作者 李洁 邹小伟
出处 《建筑经济》 2009年第5期71-74,共4页 Construction Economy
关键词 地铁项目 调查问卷 模糊AHP 风险识别 风险评价 subway projects questionnaire survey fuzzy AHP risk identification risk assessment
  • 相关文献

参考文献8

  • 1建设部城市建设司负责人谈城市轨道交通建设[EB/OL].http://www.gov.cn/jrzg/2007-07/13/eontent_683895.htm,2007-07-13.
  • 2中华人民共和国国家发展和改革委员会.综合交通网中长期发展规划[EB/OL].http://jtyss.ndrc.gov.cn/fzgh/t20080414_203812.htm,2008-12-2.
  • 3黄卫.黄卫副部长在2005地铁与地下工程技术风险管理研讨会上的讲话(2005年6月18日)[J].土木工程学报,2005,38(7). 被引量:2
  • 4Flanagan, R., Norman, G. Risk management and construction[M]. London: Blackwell Science, 1993.
  • 5AS/NZS 4360.Australia/New Zealand standard on risk management[S].2004.
  • 6Smith N. J., Merna T., Jobling P. Managing risk in construction projects[M]. London: Blackwell Science,2006.
  • 7Buckley J. J. Fuzzy Hierarchy Analysis [J]. Fuzzy Sets and Systems, 1985 (17) :233-247.
  • 8Li J. , Zou P.X.W. Risk identification and assessment in PPP infrastructure projects using fuzzy Analytical Hierarchy Process and life-cycle methodology[J]. Australian Journal of Construction Economics and Building,2008, 8 (1) :32-46.

共引文献1

同被引文献84

引证文献14

二级引证文献40

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部