摘要
城市污水泵站普遍存在淤积问题,给泵站运行、管理带来不便。结合上海市合流污水治理二期工程南线A#泵站水力模型试验研究,通过浑水试验,对原设计前池、高位井淤积规律进行了分析,提出降低前池淤积的措施。
Sedimentation generally exhisting in city sewage pumping stations causes problems and inconveniences for operation.Based on silt laden water test and combined with hydraulic model tests for A # pupmping station on the south main drain of the Second Stage of Shanghai Combined Sewage Project,sediment regularities in the pumping well and the high level discharge chamber originally designed are analyzed in this paper,and measures to reduce sediments in the pumping well are also put forward.
出处
《中国给水排水》
EI
CAS
CSCD
北大核心
1998年第1期24-26,共3页
China Water & Wastewater
关键词
污水泵站
淤积
浑水试验
污水治理
上海
Sewage pumping station
Sedimentation
Siltladen water test.