摘要 对于上部采用土层锚杆下部采用排桩支护的二级基坑,一般情况下计算时把基坑分成上下两部分各自进行,而忽略其相互影响。本文采用有限元软件PLAXIS对某二级基坑开挖的全过程进行模拟,并分析了在下部基坑开挖支护过程中上部的增量变形和锚杆轴力的变化,结果表明随基坑滑移面的转移,上部锚杆支护坡面的变形进一步增大,而各层锚杆的轴力则变化很小。 For 2-Step foundation pit supported by anchors and piles respective the upper and lower part, under normal circumstances in the calculation it is separated into two isolated parts, and ignored the interaction between. In this paper the author uses finite element software PLAXIS to simulate the whole process with a project, and analyses influences of the upper the incremental deformation and anchor axial force during the lower part excavation; has obtained as the transfer slip surface, the upper slope surface deformation increases, while the axial force of anchors on each layer changes very little.
作者 陈颖文
出处 《广东土木与建筑》 2009年第2期40-42,共3页 Guangdong Architecture Civil Engineering
关键词 锚杆 排桩 二级基坑 有限元 Anchor Pile 2-Step Foundation Pit Finite element
  • 相关文献

参考文献2

二级参考文献5

共引文献14

同被引文献12

引证文献2

二级引证文献3

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部