顶管施工工艺及关键技术 被引量:8

The top tube construction craft and key technique
下载PDF
导出
摘要 针对顶管施工是市政工程中常用的施工工艺,结合自身工程经验,给出了顶管施工工艺,提出了顶管施工的关键技术为:纠偏、中继环设置、减小摩阻力、管内通风、地面沉降控制,并分析了关键技术机理,为顶管施工及设计积累了经验。 The paper puts out top tube construction craft aiming at top tube construction cratf in the municipal engineering, joining together the oneself engineering experience, puts forward key method: rectify decline, repeating installation, the resistance of friction, tube ventilate and the ground decline control, and analyzes the key technique mechanism, backlogs construction and design experience for top tube.
出处 《山西建筑》 2009年第15期127-128,共2页 Shanxi Architecture
关键词 顶管 施工工艺 纠偏 中继环 通风 沉降控制 top tube, construction craft, rectify decline, repeater, ventilate, settlement control
  • 相关文献

参考文献3

二级参考文献11

  • 1莫筠,刘勇.浅议顶管施工技术及在某工程中的应用[J].山西建筑,2007,33(5):140-141. 被引量:3
  • 2Jancsecz S, Steiner W. Face support for a large mix-shield in heterogeneous ground conditions[A]. Tunnelling 94, conference proeedings, Institution of Mining and Metallurgy and British Tunnelling Society[C]. London: Chapman and Hall, 1994. 531 -549.
  • 3Jefferis S A. Slurrids, Grouts. Chapter 48 of Construction Materials Reference Book[M]. Doran D K. Oxford:Butterworth- Heinemann, 1992.
  • 4Anagnostou, G. and Kovari, K. Face stability in slurry and EPB shield tunneling[J]. Tunnels and Tunnelling, 1996, 28(12): 27-29.
  • 5Milligan G W E, Norris P. Pipe-soil interaction during pipe jacking. Proceedings of the Institution of Civil Engineers[J]. Geotechnicai Engineering, 1999, 137(1): 27-44.
  • 6余彬泉 陈传灿.项管施工技术(第一版)[M].北京:人民交通出版社,1998..
  • 7马·谢尔勒.项管工程[M].北京:中国建筑工业出版社,1983..
  • 8候学渊 钱达仁 杨林德.软土工程施工新技术[M].合肥:安徽科学技术出版社,1999..
  • 9李万才.大口径长距离顶管工程注浆减摩技术[J].管道技术与设备,2000(6):11-13. 被引量:37
  • 10魏纲,温晓贵.不同顶管施工工艺对深层土体移动的影响分析[J].施工技术,2003,32(1):52-54. 被引量:6

共引文献110

同被引文献24

引证文献8

二级引证文献14

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部