南水北调工程工期影响因素的问卷调查及分析 被引量:7

Questionnaire survey and analysis on delay factors of China's South-to-North Water Diversion Project
下载PDF
导出
摘要 南水北调工程是一项宏伟的跨流域水调工程,对我国经济发展起到重要作用。在对该项目业主方、设计方、承包商方、监理方等进行工期影响因素问卷调查的基础上,首先利用SPSS对问卷信度进行检验,在确保问卷可靠性的前提下,运用因子分析法简化影响工期的影响因素,并对与项目相关因素、与业主相关因素以及与承包商相关因素进行重点研究。发现各方沟通与合同管理、合同方式与招投标、项目自身特点、业主要求、工程进度款、新技术与信息的利用等方面是最为重要的工期影响因素。这些结论为相关政府主管部门提供了决策依据,同时对其他大型复杂项目群的管理也提供了有益的参考。 China's South-to-North Water Diversion is a grand project, which plays an important part in the country's economic development. Data are collected from the questionnaire feedbacks from different participants (clients, designers, contractors, consultants) of the project and statistical analysis of 94 delay factors is conducted. The reliability of the questionnaires is examined and proven by means of SPSS. Principal components analysis is used in the factor analysis to simplify the variables into several dimensions, to determine the main factors and to perform further study on the project-related, client-related and contractor-related delay factors, respectively. The results indicate that the poor communication, client's unpractical requirement, delay payment to contractors, etc. are the important factors, that the use of new technology and information should be enhanced, and that many delay factors are correlative and precautionary measures should be taken to reduce the risks in construction delays. These conclusions have provided a decision-making foundation for related government departments, as well as a valuable reference to other complex project groups in their management.
机构地区 华北电力大学
出处 《土木工程学报》 EI CSCD 北大核心 2009年第5期133-138,共6页 China Civil Engineering Journal
关键词 南水北调 建设工期 问卷调查 项目群 South-to-North Water Diversion Project (SNWDP) construction period questionnaire project groups
  • 相关文献

参考文献13

  • 1中国南水北调网.南水北凋工程总体布局[EB/OL].[2006-03-02]http://www.nsbd.gov.cn/zx/gczs/20061018/200603020012.htm
  • 2Rad P F. Delays in construction of nuclear power plants [ J ]. Energy Div., ASCE, 1979,105 ( 1 ) :33-46
  • 3Okpala D C, Aniekwu A N. Causes of high cost of construction in Nigeria [ J ]. Journal of Construction Engineering and Management, 1998,114 (2) : 233-244
  • 4Kraiem A M. Concurrent delays in construction projects [J]. Constr. Engrg. and Mgmt., ASCE, 1987,113(4): 591-601
  • 5Assaf S A, Al-Khalil M, Al-Hazmi M. Causes of delay in large building construction projects [ J ]. Mgmt. in Engrg., ASCE, 1995,11 ( 2 ) : 45-50
  • 6Manavazhi M R, Adhikari D K. Material and equipment procurement delays in highway projects in Nepal [ J ]. Internal Journal of Project Management, 2002, ( 20 ) : 627-632
  • 7Kaming P F, Olomolaiye P O, Holt G D, et al. Factors influencing construction time and cost overruns on high-rise projects in Indonesia [ J ]. Construction Management and Economics, 1997, ( 15 ) :83-94
  • 8Kumaraswamy M M, Chen D W M. Contributors to construction delays [ J ]. Construction Management and Economics, 1998, (16) : 17-29
  • 9张云波.工程项目工期延误原因分析[J].华侨大学学报(自然科学版),2003,24(4):369-373. 被引量:23
  • 10Earl B. The practice of social research [ M ]. 8th edition. Wadsworth Publishing Company, 1998

二级参考文献4

  • 1王新华.浅谈工程进度失控的原因及措施[J].建设监理,1996(6):36-37. 被引量:2
  • 2Chan D W M, Kumarawamy M M. Reason for delay in civil engineering project: The case of Hong Kong[J]. Transactions, 1996,2(3) : 1~8.
  • 3Assaf S A, AI-Khalil M, AI-Hazmi M. Cause of delay in large building construction projects[J]. Journal of Management in Engineering, ASCE, 1995,11 (2): 45 ~ 50.
  • 4张本福.工程施工进度控制[J].合肥工业大学学报(自然科学版),1999,22(4):107-110. 被引量:12

共引文献55

同被引文献86

引证文献7

二级引证文献55

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部