摘要 针对大断面浅埋黄土隧道下穿高速公路的工程特点,基于成熟的施工技术和经验,分析了造成沉降的主要因素,详细介绍了能够有效控制施工沉降的具体措施,为同类工程的设计和施工提供了可借鉴的经验。 In the light of the engineering features of underpass superhighway of shallow buried loess tunnel with large cross-section, and based on mature construction techniques and experiences, this paper analyzes some main factors causing the settlement, and introduces in detail the concrete measures for controlling the construetion settlement effectively, for providing some referential experienees for the design and construction of similar projects.
作者 连俊明
出处 《科技情报开发与经济》 2009年第12期194-197,共4页 Sci-Tech Information Development & Economy
关键词 大断面浅埋隧道 黄土隧道 下穿高速公路 沉降控制 施工技术 shallow buried tunnel with large cross-section loess tunnel underpass superhighway settlement control construction technique
  • 相关文献

同被引文献15

引证文献3

二级引证文献7

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部