基于银行授信额度的Max-NPV项目调度问题研究 被引量:8

Study on Bank Credit Limit Based Max-NPV Project Scheduling Problems
下载PDF
导出
摘要 本文对基于银行授信额度的Max-NPV项目调度问题进行研究。首先界定研究的假设条件并对文中所用到的符号进行定义;随后采用基于事件的研究方法构建了问题的整数规划优化模型;鉴于问题的NP-hard属性,设计了双层模拟退火搜索循环嵌套的启发式求解算法;最后对一个算例进行了求解分析,并讨论了银行授信额度及客户支付比例对项目收益的影响。结果表明:随着银行授信额度的提高,承包商安排项目进度自由度的增加使得其净现值得到改善,在支付比例较低的条件下项目完成时间也随之提前;当客户支付比例提高时,项目净现值单调上升,而项目完成时间呈先提前后延迟的变化趋势。 This paper involves bank credit limit based Max-NPV project scheduling problems. The assumptions of the study are identified and the notations in the paper are defined at first. Then the integer programming optimization model of the problems is constructed by using eventbased method. For the problems being NP-hard, a special heuristic composed of two nested simulated annealing searching loops is developed. Ultimately, an instance is solved and the influences of the bank credit limit and the payment proportion on the project NPV are analyzed. The outcome shows that with the increase of the bank credit limit the freedom for the contractor scheduling the project ascends, making the project NPV improved and the project completion advanced on the condition of the payment proportion being low. When the payment proportion is enhanced the project NPV climbs monotonously, and the project completion is bought forward earlier and delayed later.
出处 《管理工程学报》 CSSCI 北大核心 2009年第2期85-91,共7页 Journal of Industrial Engineering and Engineering Management
基金 国家自然科学基金资助项目(70702026) 陕西省软科学资助项目(2007KR56)
关键词 授信额度 Max-NPV项目调度 优化模型 启发式算法 credit limit Max-NPV project scheduling optimization model heuristic
  • 相关文献

参考文献14

  • 1Demeulemeester EL,Herroelen WS.Project scheduling-A research handbook[M].Boston:Kluwer Academic Publishers,2002.
  • 2Brucker P,Drexl A,M(o)hring R,et al.Resource-constrained project scheduling:notation.classification,models and methods[J].European Journal of Operational Research,1999,112:3-41.
  • 3Herroelen W,Demeulemeester E,Reyck BD.A classification scheme for project scheduling.In:Weglarz J.,editor.Project scheduling:recent models,algorithms and applications[M].Boston:Kluwer Academic Publishers 1999.p.125.
  • 4Herroelen W,Dommelen V,Demeulemeester E.Project network models with discounted cash flows:A guided tour through recent developments[J].European Journal of Operational Research,1997,100(1):97-121.
  • 5Herroelen W,Reyck BD,Demeulemeester E.Rescorce-constrained project scheduling:A survey of recent developments[J].Computers & Operations Besearch,1998,25(4):279-302.
  • 6Kolisch R,Padman R.An integrated survey of deterministic project scheduling[J].Omega,2001,29(3):249-272.
  • 7何正文,徐渝,朱少英.Max-npv项目进度问题研究评述[J].管理工程学报,2005,19(4):60-63. 被引量:23
  • 8Herroelen W.Leus R.Project scheduling under uncertainty:Survey and research potential[J].European Journal of Operational Research,2005,165(2):289-306.
  • 9张静文,徐渝,何正文,柴国荣.项目调度中的时间-费用权衡问题研究综述[J].管理工程学报,2007,21(1):92-97. 被引量:24
  • 10Ashraf ME,Ahmed AG.Finance-based scheduling of construction projects using integer programming[J].Journal of Construction Engineering and Management,2004,2:15-24.

二级参考文献74

  • 1Russell A H. Cash flows in networks[J]. Management Science, 1970,16(5) :357 ~ 373.
  • 2Grinold R C. The payment scheduling problem [J]. Naval Research Logistics Quarterly, 1972,19(1): 123 ~ 136.
  • 3Elmaghraby S E, Herroelen W. The scheduling of activities to maximize the net present value of projects [J]. European Journal of Operational Research, 1990,49: 35 ~ 49.
  • 4Herroelen W, Gallens E. Computational experience with an optimal procedure for the scheduling of activities to maximize the net present value of projects[J]. European Journal of Operational Research, 1993,65: 274 ~ 277.
  • 5Demuelemeester E, Herroelen W, Van D P. An optimal recursive search procedure for the deterministic unconstrained max-npv project scheduling problem. Technical Report, Katholieke University, 1996.
  • 6Sepil C, Kazaz B. Project scheduling with discounted cash flows and progress payments. Working Paper, Middle East Technical University,1994.
  • 7Smith-Daniels D E. Summary measures for predicting the net present value of a project. Working Paper, College of St. Thomas, 1986.
  • 8Buss A H, Rosenblatt M J. Activity delay in stochastic project networks. Working Paper, Washington University, 1993.
  • 9Yang K K, Talbot F B, Patterson J H. Scheduling a project to maximize its net present value: an integer programming approach [J]. European Journal of Operational Research, 1992,64: 188~198.
  • 10Baroum S M. An exact solution procedure for maximizing the net present value of resource-constrained projects. Ph. D dissertation,Indiana University, 1992.

共引文献61

同被引文献78

引证文献8

二级引证文献34

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部