摘要
结合汤家溪桥工程概况,确定采用扒杆法(双钓鱼法)架设,重点介绍了钓鱼法与人字扒杆法(双钓鱼法)的区别和作用及施工方案、方法和受力分析等,指出在无法使用制式架桥机架设时,值得推广使用扒杆法(双钓鱼法)。
The paper combines Tangjia river Bridge engineering general situation, which adopts person's word picking the pole method (an angling method) install, and emphases introduces the angling method with person's word picking the pole method different, function, construction project, method and suffer dint analysis etc., points out that deserves to expand usage pick the pole method(an angling method) under that can't use the type of system machine building bridge.
出处
《山西建筑》
2009年第16期307-309,共3页
Shanxi Architecture
关键词
大桥
架梁
扒杆法
双钓鱼法
受力分析
the big bridge, standing beam, person's word picking the pole method, an angling method, suffering dint analysis