摘要 在对国华锦界能源有限公司1号亚临界600MW空冷机组给水泵大联锁控制逻辑的优化过程中,展示了3台互为备用且均能从A段或B段母线起动电动给水泵的大联锁控制逻辑设计核心。57%ECR负荷下单给水泵运行单给水泵备用的大联锁试验和100%ECR负荷下双给水泵运行单给水泵备用的大联锁试验结果表明,优化后的控制逻辑设计合理、正确。 This paper presents an optimization of the interlock logic control of No. 1 600 MW subcritical air - cool unit of Guohua Jinjie Energy CO. ,Ltd. The interlock logic design core it revealed has a control of three feed water pumps that are standby for one another and can all be started up from section A or B of the bus - bar. Tests on the electric pump interlock were conducted under the different conditions,one is with one pump in operation while the other was standby under 59%load,and the other is that two pumps were in operation while one pump is standby under 100 % load. The test results have proved that the logic design after optimization is rational and correct.
出处 《热力发电》 CAS 北大核心 2009年第5期94-97,共4页 Thermal Power Generation
关键词 火电厂 亚临界 空冷 600 MW机组 给水泵大联锁 给水控制系统 汽包水位 feed water pump interlock, feed water control system, optimization, drum level
  • 相关文献

参考文献2

  • 1张方琦.陕西国华锦界煤电工程给水系统设计说明书[Z].西北电力设计院,2005.
  • 2张伟.陕西国华锦界能源有限公司1号机组DCS逻辑[Z].上海电力建设启动调整试验所,2006.

同被引文献28

引证文献3

二级引证文献15

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部