龙固矿深立井大流量工作面预注浆堵水研究 被引量:4

A study on the pre-grouting in deep mine for water blockage in Longgu Coal Mine
下载PDF
导出
摘要 针对龙固矿井高压大流量突水的特点,提出"分次注浆,逐步降水"原则,对龙固矿井副井Ⅲ含中进行预注浆堵水项目中的注浆材料选择和注浆工艺等进行了研究,得到较为合理的浆液配比方案。 In view of the characteristics of big water inflow at high pressure in Longgu Coal Mine, a technical solution is proposed in this paper on the principle of "gradual reducing water inrush by separate groutings". A study on the selection of grouting materials and grouting process during the pre-grouting project for water blocking in the Ⅲ water bearing strata in sinking the auxiliary shaft of Longgu Coal Mine. The results obtained produces rationalized formula of grout.
作者 徐栓祥
出处 《中国煤炭》 北大核心 2009年第5期54-56,共3页 China Coal
关键词 深立井 大流量 预注浆 龙固矿 deep vertical shaft, big inflow, pre-grouting, Longgu Coal Mine