期刊文献+

火电厂基建项目施工标段划分方法的探讨 被引量:1

Inquisition into Construction Bidding Section Division of Thermal Power Plant Capital Project
原文传递
导出
摘要 标段划分是工程施工招标工作过程中的重要环节,火电基建项目施工标段的划分与其他工程有所不同。文章从施工管理模式、标段合理划分的意义、必要性、可行性以及常见的标段划分方法及影响因素等方面进行了阐述,结合具体项目实际探讨了标段划分的思路和分析模型。 Bidding section division is an important link in project construction bidding process. Construction bidding section division for thermal power capital project is different from other projects. The paper describes in following aspects: construction management mode, significance, necessity, feasibility of bidding section rational division, conventional division method and impact factors, etc. It also discusses thinking way and analysis model for bidding section division in combination with practical project.
出处 《电力建设》 2009年第6期84-86,共3页 Electric Power Construction
关键词 标段划分 工程造价 火电施工 bidding section division engineering cost thermal power construction
  • 相关文献

参考文献10

二级参考文献6

  • 1McKim R, Hegazy T, Attalla M. Project performance control in reconstruction projects[J]. Journal of Construction Engineering and Management, 2000, 126 (2): 137-141.
  • 2Rwelamila P D, et al. Total systems intervention: An integrated approach to time, cost and quality mawgement[J]. Construction Management and Economics, 1995, 13: 235-241.
  • 3Babu A J G, Suresh N. Project management with time, cost, and quality considerations[ J]. European Journal of Operational Research, 1996, 88 (2): 320-327.
  • 4Do Ba Khang, Yin Mon Myint. Time, cost and quality trade-off in project management: A case study[J]. International Journal of Project Management, 1999, 17(4): 249-256.
  • 5Shih-Wen Hsiao. Fuzzy logic based decision models for product design[J]. International Journal of Industrial Ergonomics, 1998,21: 103-116.
  • 6唐殿峰,秦桂娟.工程项目质量工期费用控制模拟系统[J].沈阳建筑工程学院学报,1998,14(2):158-161. 被引量:16