摘要
随着变电站计算机监控系统的发展,监控系统技术日趋成熟,已具备条件统一其设计原则。对国家电网公司110~500kV变电站二次系统典型设计规范中计算机监控系统部分的编制过程及要点进行介绍。对计算机监控系统的配置方案、组屏方案、系统功能及数据采集信号内容提出建议。监控系统典型设计统一了设备规范,减少了设备形式,方便设备维护,宜在工程实际中推广应用。
With the development of supervisory control system technology, the design principle of supervisory control system (SCS) should be unified. The compiling process and main points of typical design of supervisory control system were introduced for 110-500 kV Substation in SGCC. The suggestions were presented for system configuration, principle of equipment location, system functions and contents of the data acquisition. Typical Design unified the specification of the supervisory control system, reduced the type of equipment and provided convenience for maintenance work. Typical Design could be applied comprehensively in project.
出处
《中国电力》
CSCD
北大核心
2009年第6期74-78,共5页
Electric Power
关键词
计算机监控系统
系统配置
数据采集
通信接口
supervisory control system ( SCS )
system configuration
data acquisition
communication interface