摘要
文章介绍了武广铁路客运专线XXTJⅤ标采用移动模架现场浇注32m后张预应力双线整孔简支箱梁快速施工技术,采用网络计划技术对移动模架快速制梁施工进行优化管理,达到了连续五孔每孔11d的施工水平,可为类似工程施工提供一定的经验和指导。
The post-tensioned prestressed double-track simply-supported beam (32m in span) at Bid XXTJ of Wuhan-Guangzhou Passenger Line was east in place with mobile formwork. During which the technology of network planning was used to enable a construction progress of 11 days for each beam (with the fabrication of five beams in succession). The work experience introduced in the paper is of referential value for similar engineering.
出处
《安徽建筑》
2009年第3期49-50,共2页
Anhui Architecture
关键词
网络计划技术
移动模架
32m双线简支梁
快速施工技术
network planning
mobile formwork
double-track simply-supported beam(32m in span)
swift fabrication