摘要
以神华米东(2×300MW)煤矸石热电联产工程为例,分析评价范围内多个点源对关心点的大气污染物浓度贡献及替代小锅炉的削减量,预测拟建火电厂投运后关心点的叠加浓度值,在实际工作中为相关问题提供一定的借鉴经验。
This paper takes Shen Hua Midong gangue thermoelectricity union project (2×300MW) as example, analyze evaluated scope that multi - pollution sources contribution to the concentrate points and reduction of small boilers be replaced. Forecasted the thermal power plants put into operation that the area of overlay concentration of atnlospheric pollutants in the area, which provide a reference for the experience of related issues to the work and research.
出处
《新疆环境保护》
2009年第1期18-21,共4页
Environmental Protection of Xinjiang
关键词
火电厂
环境影响评价
大气污染物
叠加
削减
thermal power plant
environmental impact assessment (EIA)
pollutants
overlay
cut