针对湘钢三中央变电站220kV备用电源自投装置存在的问题,提出了新的方式和设想.分析采用新的方式后,停电时间由3.5s缩短至0.04~0.09s的可行性.同时还提出在SF6断路器的变电站,自投装置应采用的方式.
New modes and suggestions are proposed on the basis of problems of automatic turning on devices of 220kv stand-by power of No. 3 central substation of Xiangtan Iron and Steel Plant. Feasibility of reducing outage time from 3. 5s to 0. 04-0. 09s is analyzed when a new method is used. It proposes suitable modes for automatic turning on devices In a substation with SF6. disconnectors.
出处
《冶金动力》
1998年第2期6-10,共5页
Metallurgical Power