摘要
填石路基方案在软土地基道路施工的应用中,由于填石路基沉降量大,石料与土壤界面难以确定,影响填石路基工程量计量的准确性。该文采用了三种不同确定工程量的方法,探讨能准确、及时、有效地反映填石路基工程量的方案。
In the application of filling stone roadbed scheme in the construction of soft soil roadbed,it is hard to determine the interface of stone and soil because of the great settlement of filling stone roadbed so as to influence the accuracy of measuring the engineering quantity of filling stone roadbed. The article uses three different methods to determine the engineering quantity,and discusses the schemes able to correctly,efficiently reflect the engineering quantity of filling stone roadbed in time.
出处
《城市道桥与防洪》
2009年第6期162-163,共2页
Urban Roads Bridges & Flood Control
关键词
填石路基
沉降值理论计算
工程量
计量方法
沉降标
探地雷达
filling stone roadbed
theoretical calculation of settlement value
engineering quantity
measuring method
settlement gauge
detecting ground radar