在水电站前期工作中,对拟建区域内的工程地质勘察工作十分重要,要求具有水电站工程勘察和设计资质的设计单位一定要深入开展工程地质勘察工作,为坝址、坝型的选择提供可靠的数据和地勘成果,以使工程能够安全顺利地进行。
In early preparation works of hydropower station,engineering geological investigations in the proposed dam area are very crucial.Therefore,design organization with hydropower project investigation and design qualifications is required to carry out further engineering geological investigations to provide reliable data and geological investigation results for selection of damsite and dam type so as to ensure hydropower project to be constructed in safe and successful way.
出处
《四川水力发电》
2009年第3期76-77,110,共3页
Sichuan Hydropower
关键词
小龙潭水电站
坝址
坝型选择
hydropower station
selection of damsite and dam type