溜槽技术在长距离有轨斜井施工中的应用 被引量:11

Application of Chute Transportation Technology in Long Inclined Shaft with Rail-bound Transportation System
下载PDF
导出
摘要 以象山特长隧道3#斜井有轨运输混凝土输送施工技术为例,介绍敞口式溜槽沿长大、陡坡斜井向下输送混凝土的施工技术。此项技术的成功应用,极大地提高了有轨斜井混凝土的运输能力,打破了有轨斜井施工过程中,由于混凝土运输能力受限而制约仰拱、填充及二衬混凝土施工进度的瓶颈,有较好的推广使用意义和参考价值。 Taking the concrete transportation technology used in No. 3 inclined shaft of Xiangshan extra-long tunnel as an example, the authors present the concrete delievery technology by using open chute along the long and steep inclined shaft. The successful application of this technique greatly improved the transportation capacity of the inclined shaft installed with rail-bound transportation system. Furthermore, this technique solved the problem of limited concrete transportation capacity, which restricts the construction schedule of invert, filling and secondary concrete lining. The technology should be promoted or referred for other projects in the future.
出处 《隧道建设》 2009年第3期352-355,共4页 Tunnel Construction
关键词 长距离、陡坡 有轨斜井 溜槽技术 long and steep slope inclined shaft with rail-bound transportation system chute technology
  • 相关文献

参考文献9

二级参考文献3

  • 1洪晓华.矿井运输提升[M].中国矿业大学出版社,2002..
  • 2TB10204-2002/J163-2002,铁路隧道施工规范[S].
  • 3兰州交通大学岩土研究所.关于对乌鞘岭隧道F7断层现行施工工艺的讨论[Z].兰州:兰州交通大学岩土研究所,2005.

共引文献43

同被引文献52

引证文献11

二级引证文献16

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部