摘要 对于采用排水固结法加固饱和软粘土地基,在理想井的情况下减小排水板间距可有效地缩短固结时间,但是在设计中也要考虑塑料排水板间距对工期和造价的影响.因此,对天津港真空预压法中塑料排水板打设间距设计时应考虑的加固时间及造价进行了分析,并提出相应的处理方法,具有一定的应用价值. For the saturated soft clay foundation consolidated by the drainage consolidation method, to reduce the distance of plastic drainage plate would effectively shorten the time for consolidation of soil 'wherever there are ideal wells. However, the distance of plastic drainage plate varies with time and cost. It is suggested that the optimization between the distance of plastic drainage plate, time and cost in TianJin Port area may be practical.
作者 朱福明
机构地区 天津港建设公司
出处 《江西水利科技》 2009年第2期116-118,145,共4页 Jiangxi Hydraulic Science & Technology
关键词 真空预压 排水板间距 加固时间 造价 Vacuum preloading Distance of plastic drainage plate Time Cost
  • 相关文献

参考文献4

二级参考文献5

  • 1谢康和,曾国熙.砂井地基的优化设计[J].土木工程学报,1989,22(2):3-12. 被引量:13
  • 2刘爱民.北方石油库区地基处理加固效果检验报告[R].天津港湾工程研究所,2003..
  • 3于志强.天津港南疆石化码头成品油库区软基加固效果检验报告[R].天津港湾工程研究所,1993..
  • 4陈永源.天津港南疆煤码头翻车机房软基加固效果检验报告[R].天津港湾工程研究所,1995..
  • 5刘爱民.天津港南疆11号通用散货泊位工程铁路车场区地基处理加固效果检验报告[R].天津港湾工程研究所,2003..

共引文献22

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部