摘要 阿联酋NAJMAT方块码头工程大部分位于陆地,海域部分采用临时围堰以形成干地施工条件。经过各方面的比较,采用国内普遍使用的水力充填砂袋作为临时施工围堰。文章详细介绍了砂袋围堰的施工情况和实施效果。结果表明,砂袋围堰在本工程实施取得了较好的止水效果。供各位同行参考。 The major part of the block Quay Wall of NAJMAT project in UAE was located on land; a temporary cofferdam was proposed to achieve a 'dry' construction condition in the sea. By comparison and analyses based on site conditions, sand-bag by hydraulic fill which had been widely used in China was introduced to form a temporary cofferdam for the work. This paper has a detailed description on construction and final results of sand bag cofferdam. The result shows that, the application of sad bag cofferdam in this project has good stop-water effects, and provides reference for engineering personnel in the same field.
出处 《中国港湾建设》 北大核心 2009年第3期45-48,共4页 China Harbour Engineering
关键词 砂袋围堰 方块码头 干地施工 sand bag cofferdam block quay wall 'dry' construction
  • 相关文献

参考文献2

共引文献4

同被引文献29

引证文献6

二级引证文献9

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部