摘要 应用环境应力分析法和MIL-HDBK-217标准,对国内某典型保护设备进行插件级的基本可靠性评估分析。在对其可靠性进行客观评价的基础上,找出存在的薄弱环节,为二次设备运行、检修、维护提供了重要参考。 The basic reliability of the relay was objective evaluated based on stress analysis. The reliability prediction standard is MIL-HDBK-217. Based on the evaluation result, the weaknesses in the relay were found, which would be very useful for operation, examination and maintenance.
出处 《浙江电力》 2009年第3期16-19,共4页 Zhejiang Electric Power
关键词 可靠性 环境应力 评估 变电站 二次设备 reliability stress evaluation substation secondary equipment
  • 相关文献

参考文献9

  • 1曾克娥.电力系统继电保护装置运行可靠性指标探讨[J].电网技术,2004,28(14):83-85. 被引量:61
  • 2Aderson P, E O Schweitzer. Reliability Analysis of Transmission Protection using Fault Tree Methods[J]. Schweitzer Engineering Laboratories (SEL), Inc, 1997.
  • 3Aderson P. Power System Protection[M]. IEEE Press, 1998.
  • 4Kumm J, Hou D Q. Predicting the optimum routine test interval for protective relays[J] . IEEE Transactions on Power Delivery, 1995, 10(2) : 659- 665.
  • 5Billinton R, Fotuhi - Firuzabad M, Sidhu T. Determination of the optimum routine test and self- checking intervals in protective relaying using a reliability model[J] . IEEE Transactions on Power Systems, 2002, 17(3): 663- 669.
  • 6Anderson P, Chintaluri G, Magbuhat S, et ah An improved reliability model for redundant protective systems - Markov models[J]. IEEE Transactions on Power Systems, 1997, 2.
  • 7贺家李,郭征,杨晓军,李永丽.继电保护的可靠性与动态性能仿真[J].电网技术,2004,28(9):18-22. 被引量:51
  • 8李永丽,李致中,杨维.继电保护装置可靠性及其最佳检修周期的研究[J].中国电机工程学报,2001,21(6):63-65. 被引量:113
  • 9Mil-Hdbk-217 FN2, Reliability Prediction of Electronic Equipments[S].

二级参考文献14

共引文献202

同被引文献29

引证文献3

二级引证文献13

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部