摘要
对深基坑施工中深层土体水平位移的一些测试技术问题进行分析和探讨.指出应变式测仪斜精度可满足一般工程需要;测点距应定为导轮距.给出了“跳槽”的处理方法.
Some monitoring techniques for soil deep lateral movement during deep evcavation are analysed.It is shown that the accurancy of strain clinometer is low,but it can be applied to some small projects.Some other problems are discussed as well.
出处
《河海大学学报(自然科学版)》
CAS
CSCD
1998年第3期120-122,共3页
Journal of Hohai University(Natural Sciences)
关键词
深基坑
测斜技术
测斜仪
精度
变形观测
deep foundation pit
monitoring techniques of deep lateral moverment
clinometer
accuracy