摘要 联补水电站施工过程中,左岸山体崩坡积层出现裂缝.通过对地表裂缝发育特征的分析,发现裂缝均为拉张性质,表现出典型的土体蠕变特征,各部位裂缝成因略有差别.通过地表以及深层变形监测数据分析,并采用离散元模拟左岸山体斜坡变形失稳的全过程等,提出了左岸山体整体稳定、无明显的整体变形破坏迹象的重要结论,为工程设计及枢纽安全运行提供了依据. The colluvium of left bank hilly region cracked in the construction of Lianbu Hydropower Station, which are proved be tension Cracks because of different reasons in different regions based on the analysis on crack growth of earth surface. The paper draws the conclusion that there is no deforming phenomenon as a whole in left bank hilly region after analysing the monitoring data of surface and underground deformation by gliding simulation on discrete mode.
作者 黄维 任奎
出处 《浙江水利水电专科学校学报》 2009年第2期1-6,共6页 Journal of Zhejiang Water Conservancy and Hydropower College
关键词 联补水电站 闸坝 左岸山体 整体稳定性 Lianbu Hydropower Station pier hilly region of left bank overall stability
  • 相关文献

参考文献2

二级参考文献23

共引文献98

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部