摘要
介绍了国电北仑电厂三期工程超超临界机组热控施工特点,主要包括分区域和分系统管理、施工示范工艺卡管理、二次设计、洁净化安装和高温高压部件安装等方面,可为火电厂热控施工管理提供参考。
The paper describes USC unit thermal construction characters of Guodian Beilun power plant project, phase Ⅲ, including divided area and system management, construction demonstration process card, secondary design, cleaned installation and HTHP component installation, which can be a reference for thermal-contrul construction management.
出处
《电力建设》
2009年第7期83-87,共5页
Electric Power Construction
关键词
超超临界机组
热控施工
工程管理
USC unit
thermal-control construction
engineering management