摘要 电网规模的不断扩大,设备急剧增多,加上状态检修等约束条件的引入,人工计划安排越来越困难。为此引入优化检修计划模型。它采用了整数编码、随机交叉、有约束的变值变异的策略及有效的适值函数,以遗传算法进行求解。实际算例表明,能有效地优化设备的检修,达到了避免重复停电和提高电网安全的目的。 Continueous expansion of power grid results the amount of equipment increases rapidly and artificial planning of equipment maintenance under the restiction of status becomes difficult. Thus an optimized mode of scheduling is introduced. It applies integer coding, stochestic crossing, tactics of restricted changeable variation, effective calibration function, and making solution via improved genetic algolithm. Example calculation denotes that this planning model can effectively optimize maintenance work, avoid repeatition outage of power equipment and maintain the safe operation of power grid.
作者 李党
出处 《广东输电与变电技术》 2009年第4期33-37,共5页 Guangdong Power Transmission Technology
关键词 供电设备检修 遗传算法 检修计划 优化 Power grid equipment Maintenance planning optimization Genetic algorithm
  • 相关文献

参考文献7

二级参考文献31

  • 1冯永青,张伯明,吴文传,李尹,孙宏斌,林鄂华.电力市场发电机组检修计划的快速算法[J].电力系统自动化,2004,28(16):41-44. 被引量:37
  • 2孟凡强,许克明,王亮,李艳丽,张海燕.电力市场下的发电机组状态检修[J].电力系统自动化,2004,28(17):41-44. 被引量:14
  • 3黄弦超,舒隽,张粒子,朱刚毅.免疫禁忌混合智能优化算法在配电网检修优化中的应用[J].中国电机工程学报,2004,24(11):96-100. 被引量:61
  • 4王健,文福拴,杨仁刚.基于机会约束规划的发电公司最优检修策略[J].电力系统自动化,2004,28(19):27-31. 被引量:17
  • 5[2]Endrenyi J. The present status of maintenance strategies and the impact of maintenance on relaibility [J ]. IEEE Transaction on Power Systems, 2001,16(4): 638- 646
  • 6[3]Haussman W. Sequential decision problems:a model to exploit existing forecasters [J ]. Management Science, 1969,16(2): 93- 111
  • 7[5]Puterman M L. Markov Decision Process: Discrete Stochastic Dynamic Programming [M]. John Wiley and Sons Inc, 1994
  • 8[6]Howard Ronald A. Dynamic Probabilistic Systems Volume Ⅱ: Semi-Markov and Decision Process[M ].John Wiley & Sons Inc,1971
  • 9[9]Anders G J, Endrenyi J, Ford G L, et al. A probabilistic model for evaluating the remaining life of electrical insulation in rotating machines[J].IEEE Transaction on Energy Conversion, 1990, 5(4):761-767
  • 10[10]Anders G J, Endrenyi J, Yung C. Risk-Based planner for asset management [ J ]. IEEE Computer Applications in Power, 2001,14 (4): 20-26

共引文献111