摘要
广西某电解铝车间电解槽沉降基础在采用直孔帷幕灌浆加固的基础上,利用斜孔在有限空间进行二次灌浆加固复位,通过合理控制灌浆压力和灌浆量或间歇灌浆等措施,实行测量跟踪观测控制每次灌浆的抬升量,成功地将电解槽沉降基础抬升复位。
Based on the straight hole curtain grouting reinforcement for an electrolytic cell foundation settlement, the second cementation was applied for reinforcement and restoration by inclined hole. By the means of reasonable control on grouting pressure & grouting amount and with the intermittent grouting technology, every lifting level was monitored and controlled ; electrolytic cell foundation settlement was successfully restored.
出处
《探矿工程(岩土钻掘工程)》
2009年第7期53-56,59,共5页
Exploration Engineering:Rock & Soil Drilling and Tunneling
关键词
电解槽沉降基础
帷幕灌浆
斜孔二次灌浆
加固复位
跟踪观测
electrolytic cell foundation settlement
curtain grouting
the second cementation by inclined hole
reinforcement and restoration
tracking observation