摘要
北京丰联广场大厦冬期地下防水施工中,采用石棉板代替抹灰找平层,用纤维板临时代替抹灰保护层,边坡混凝土保护层施工加铺钢板网等方法,加快了施工进度,简化了施工,取得了良好的防水效果。
The construction technology of winter season underground wa-terproofing work for the Beijing Full Link Square Mansion project has been adopted effectively with the following methods, namely: 1, application of asbestos board to substitute plastering and screeding work, 2,utilization of fibre board to substitute temporary cement mortar protective layer, 3, construction of side - slope concrete protective layer with steel mesh. These methods have shortened time schedule of construction, simplified operational procedures of construction, and achieved good result in waterproofing efficiency.
出处
《建筑技术》
北大核心
1998年第4期242-243,共2页
Architecture Technology
关键词
地下防水
垫层
防水卷材
石棉板
冬期施工
广场
underground waterproofing construction, bedding course, waterproofing roll-roofing, asbestos board, fibre board