期刊文献+

盾构法和浅埋暗挖法结合建造地铁车站的模型试验 被引量:37

MODEL TEST ON METRO STATION CONSTRUCTED BY COMBINATION OF SHIELD METHOD AND SHALLOW-BURIED TUNNELING METHOD
下载PDF
导出
摘要 针对目前国内区间盾构施工和车站施工工期矛盾的问题,提出盾构法和浅埋暗挖法结合建造地铁车站的新方案。通过1∶10大比尺模型试验研究,介绍模型地层、开挖方案和支护方案的模拟,比较真实地再现新型车站的施工过程。得到盾构管片应变、收敛变形和洞周土体变位在整个车站施工过程中的变化规律。试验结果表明在模型地层构造和地应力的条件下,采用试验中的施工开挖方案和支护方案能够保证车站洞室在整个施工过程中的安全稳定,证明提出的新型车站施工技术是可行的。 In order to solve the contradiction of construction time limit for running tunnel constructed by shield method and station in China, the new-style station construction method, in which the station is constructed by shield method and mining method, is put forward. In the model test study with scale ratio of 1 ; 10, the simulation of model stratum, excavation scheme and tunnel support scheme are introduced; and the station construction process is reappeared. The variation laws of strain, convergence of the shield segments and displacement of the soil around station tunnel are achieved. The results show that the excavation and tunnel support schemes can ensure the safety of the station under the conditions of model stratum and in-situ stress, by which the feasibility of station construction technology recommended is proved as well.
出处 《岩石力学与工程学报》 EI CAS CSCD 北大核心 2009年第8期1629-1639,共11页 Chinese Journal of Rock Mechanics and Engineering
基金 北京市科技计划项目资助(D0604003040921)
关键词 隧道工程 盾构法 浅埋暗挖法:地铁车站 施工过程 模型试验 变化规律 tunnelling engineefing shield method shallow-buried tunneling method: metro station construction process model test variation rules
  • 相关文献

参考文献15

二级参考文献58

共引文献219

同被引文献196

引证文献37

二级引证文献183

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部