基于分支定界法的多资源约束下项目进度规划 被引量:5

Project Scheduling under Multiple Resource Constraints Based on Branch and Bound Procedure
下载PDF
导出
摘要 基于分支定界法的思想提出了一种新的精确求解多资源约束下项目进度规划问题的最优化算法。首先依据网络图中活动的逻辑关系和资源约束进行分支构建搜索树,然后通过基于广探法思想提出的优选原则对搜索树中的分支节点进行分析比较,淘汰劣解进一步缩小搜索空间并提高求解效率,最终可获得最优解。最后通过实例进行分析表明算法在求解多资源约束条件下项目进度规划问题的有效性,同时对于资源平衡优化问题以及合理权衡项目竣工时间与资源配置两者之间关系都有一定的现实指导意义。 In this paper a new exact algorithm is proposed for solving project scheduling problems under multiple resource constrains which is based on the branch and bound procedure. The enumeration tree is generated by the feasible branches emanating from a parent node subject to precedence and resource constraints in the network. Then the feasible branches are evaluated by using the pruning rules based on the breadth-first search solution strategy, and the worse ones will be eliminated from the enumeration tree while the better will continue branching until they get the best solution. It is proved by examples that this new exact algorithm is efficient, providing a method for resource balance and a reasonable trade-off between resource allocation and duration.
出处 《北京理工大学学报(社会科学版)》 CSSCI 2009年第4期41-45,共5页 Journal of Beijing Institute of Technology:Social Sciences Edition
基金 国家自然科学基金(70772057)
关键词 分支定界法 资源约束 项目进度规划 资源配置 branch and bound procedure resource constraints project scheduling resource allocation
  • 相关文献

参考文献14

  • 1白思俊.多资源约束的网络计划的启发式优化方法[J].系统工程理论与实践,1995,15(7):42-47.
  • 2杨永清,许先云.多资源约束下的工序排序准则及其优化[J].系统工程理论与实践,1995,15(5):28-31. 被引量:2
  • 3蒋根谋.多资源约束下包含资源使用顺序关系最优施工计划的确定[J].铁道科学与工程学报,2005,2(3):56-62. 被引量:8
  • 4林琳,姚郁.多资源约束下的多项目作业调度问题研究[J].哈尔滨工业大学学报,2007,39(7):1045-1049. 被引量:9
  • 5Shukla Sanjay Kumar, Son Young Jun ,M.K. Tiwari. Fuzzy-based adaptive sample-sort simulated annealing for resourceconstrained project scheduling[J]. International Journal of Advanced Manufacturing Technology, 2008, 36(9-10): 982-995.
  • 6J.F. Goncalves, J.J.M. Mendes, M.G.C. Resende. A genetic algorithm for the resource constrained multi-project scheduling problem[J]. European Journal of Operational Research, 2008, 189(3): 1171-1190.
  • 7Homberger, J.. A multi-agent system for the decentralized resource- constrained multi-project scheduling problem [J]. International Transactions in Operational Research, 2007, 14(6): 565-589.
  • 8Shou, Yongyi. A bi-directional ant colony algorithm for resource constrained project scheduling [A]. IEEM 2007:2007 IEEE International Conference on Industrial Engineering and Engineering Management[C], United States, 2007: 1027-1031.
  • 9Ozdamar, L., and Ulusou,G.. A survey on the resource-constrained project scheduling problem. IIE Trans., 1995, 27: 574-586.
  • 10ARNETHESEN.运筹学的计算机方法[M].薛华成,译.清华大学出版社,1986:3.

二级参考文献26

  • 1林剑柠,吴慧中.基于遗传算法的网格资源调度算法[J].计算机研究与发展,2004,41(12):2195-2199. 被引量:70
  • 2《运筹学》教材编写组.运筹学[M].北京:清华大学出版社,1997..
  • 3Davis E W,Patterson J H. A comparison of heuristic and optimum solutions in resource-constrained project scheduling [J]. Management Science, 1975, 21(8): 944-955.
  • 4Patterson J. A comparison of exact procedures for solving the multiple constrained resource project scheduling problem [J]. Management Science, 1984, 30(7): 854-867.
  • 5Brucher P, Knust S, Schoo A, et al. A branch and bound algorithm for the resource constrained project scheduling problem [J]. European Journal of Operational Research, 1998, 107: 272-288.
  • 6Demeulemeester E L, Herroelen W. A branch-and-bound procedure for the multiple resource-constrained project schedule problem [J]. Management Science, 1992, 38: 1 803-1 818.
  • 7Dorndorf U, Pesch E, Phan-Huy T. A branch-and-bound algorithm for the resource-constrained project scheduling problem [J]. Mathematical Methods of Operations Research, 2000, 52: 413-439.
  • 8Mingozzi A, Maniezzo V, Ricciardelli S, et al. An exact algorithm for the resource-constrained project scheduling problem based on a new mathematical formulation [J]. Management Science, 1998, 44: 714-729.
  • 9Sprecher A. Scheduling resource-constrained projects competitively at modest memory requirements [J]. Management Science, 2000, 46: 710-723.
  • 10Bruker P, Drexl A, Mhring R, et al. Resource-constrained project scheduling: notation, classification, models, and methods[J]. European Journal of Operational Research, 1999, 112:3-41.

共引文献22

同被引文献46

引证文献5

二级引证文献24

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部