摘要
介绍老渡口水电站面板堆石坝工程坝基趾板混凝土防渗墙施工的特点和难点,通过精心的组织,合理确定施工方案、严格控制质量技术措施,开创了防渗墙在动水中施工的先例,确保了防渗墙如期完工的目标。
The technical difficulties in construction of impervious wall in Laodukou CFRD built in flowing water are described, these difficulties are overcome by eleborately drawing up construction scheme and strictly carrying out quality control in every construction procedure.
出处
《湖北水力发电》
2009年第3期49-52,共4页
Hubei Water Power
关键词
老渡口水电站
面板堆石坝
趾板
混凝土防渗墙
施工
Laodukou Hydropower Station
concrete faced rockfill dam ( CFRD )
toe slab
concrete impervious wall
construction