摘要
从吊装机械、工期、作业流程、相关计算、关键性工作等方面对贵港电厂一期2×600 MW燃煤机组发电机定子所采用的行车+液压提升装置劳辛格联合吊装方案进行论述。
Taking Guigang Power Plant first phase oi 2 ×600 MW project as an example, the hoisting schemes combined traveling crane of coal-fired generator stator with tightwire hydraulic-roof crane technics are discussed from the points of hoisting machine, construction period, relative calculation, and essential works.
出处
《山西电力》
2009年第4期32-34,共3页
Shanxi Electric Power
关键词
定子
劳辛格
吊装
stator
loxic
hoisting