基于实时监控的高心墙堆石坝施工仿真理论与应用 被引量:12

Theory and application of construction simulation for high core rock-fill dam based on real-time monitoring
下载PDF
导出
摘要 文中提出了基于实时监控的高心墙堆石坝施工仿真理论,基于实时监控系统所监控的道路运输与坝面填筑实时的施工方法、数据,通过对系统数据库信息的自动读取,可以实时更新仿真模型参数与边界条件,保证仿真贴近实际施工,实现对施工进度较精确的预测。研究成果应用于西南某水电工程中,为该工程大坝的现场施工与管理提供技术支持。 A theory of construction simulation for high core rock-fill dam based on the real-time monitoring is put forward herein. In accordance with the real-time construction methods and data of the transportation system and the dam filling system monitored by the real-time monitoring system, the parameters and boundary conditions of the simulation model can be renewed to ensure the simulation to be more close to the actual construction and then realize the more precise prediction of the construction progress through the automatic reading of the information from the database of the system. This study achievement has been applied to a hydropower construction project in the Southwest China and a better technical support has been provided for the construction and management in site as well.
作者 钟登华 张平
出处 《水利水电技术》 CSCD 北大核心 2009年第8期103-107,共5页 Water Resources and Hydropower Engineering
基金 国家杰出青年科学基金(50525927) 国家自然科学基金(50879056)
关键词 高心墙堆石坝 实时监控 施工仿真 high core rock-fill dam real-time monitoring construction simulation
  • 相关文献

参考文献8

  • 1Hijazi A M, AbouRizk S M, Halpin D W. Modeling and simulating learning development in construction [ J ]. Constr. Eng. Manage, 1992, 118(4) : 685-700.
  • 2Lu Ming. Simplified discrete-event simulation approach for construction simulation[ J ]. Journal of Construction Engineering and Management, 2003, 129(5): 537-546.
  • 3Balqies S. Applied System Simulation: a Review Study [ J ]. Information Sciences, 2000, 124 : 173-192.
  • 4Lee K, Fishwick P A. OOPM/RT: a muhimodeling methodology for real-time simulation[J]. ACM Transactions on Modeling and Computer Simulation, 1999, 9(2): 141-170.
  • 5马洪琪,曹克明.超高面板坝的关键技术问题[J].中国工程科学,2007,9(11):4-10. 被引量:42
  • 6Sahil Malik. Pro ADO. NET 2. 0[ M]. New York: Apress, 2005, 470- 500.
  • 7Zhong D H, Li J R, Zhu H R, et al. Geographic information system-based visual simulation methodology and its application in concrete dam construction processes [ J ]. Journal of Construction Engineering and Management, ASCE, 2004, 130(5) : 742-750.
  • 8钟登华,胡程顺,张静.高土石坝施工计算机一体化仿真[J].天津大学学报(自然科学与工程技术版),2004,37(10):872-877. 被引量:17

二级参考文献11

共引文献57

同被引文献84

引证文献12

二级引证文献90

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部