扰动地层上围堰防渗墙施工工艺及特点

Construction technique and characteristics of cofferdam anti-seepage wall on disturbed strata
下载PDF
导出
摘要 KLSK水利枢纽采用河床布置碾压混凝土重力坝及右岸布置引水发电系统的格局。上下游围堰处河床覆盖层厚达13m左右,受多年人工采金影响,已被严重扰动、分选,基础具有强透水性。采用槽孔防渗墙,结合灌浆加固槽孔、旋挖成墙的施工工艺,较好地解决了围堰基础处理上的难题。 KLSK Hydraulic Complex is designed with RCC gravity dam on fiver bed and diversion power generation system by the fight bank. The 13m-thick overburden layers at the positions of upstream and downstream cofferdams had been seriously disturbed and separated due to many years of manual gold mining. In view of the strong permeability of foundation, slotted anti-seepage wall design was adopted, combined with the construction technique of slot reinforcement by grouting and wall forming by rotary dredgingx, rendering relatively good effeet.
作者 蒋兵
出处 《广西水利水电》 2009年第4期47-49,53,共4页 Guangxi Water Resources & Hydropower Engineering
关键词 围堰 防渗墙 砂砾石灌浆 扰动地层 Cofferdam anti-seepage wall sandy gravel grouting disturbed strata
  • 相关文献

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部