摘要
针对近几年湖南省投产的国产引进型600MW汽轮机在调试中发生的主要问题进行分析,介绍了采取的对策,供同类型机组设计、安装、调试和运行借鉴。
This paper analyzed the main problems existing in domestic imported 600 MW steam turbine commissioning and in- troduced relevant countermeasures, offering reference for unit design, installation, commissioning, and operation of similar units.
出处
《湖南电力》
2009年第4期49-51,共3页
Hunan Electric Power
关键词
600
MW
汽轮机
调试
600 MW
steam turbine
commissioning