摘要
介绍了地质条件恶劣的高海拔地区送电线路施工的主要工艺,详细说明了在高海拔地区进行施工测量、导线及避雷线架设、电杆起立以及施工组织管理等应该注意的问题。
Introduces the main techniques of transmission line construction for poor geological condition and high altitude area, expounds the attentive problems of construction measurement, extending the leads and arrester lines, poles of power line erection and the construction management in high altitude area.
出处
《宁夏电力》
2009年第4期31-33,共3页
Ningxia Electric Power
关键词
高海拔地区
架空线
送电线路
施工技术
high altitude area
overhead hne
power line
construction technique