摘要
文章介绍了某电缆隧道从东西两座京广线铁路桥侧下方通过的工程实践。通过采用格栅喷射混凝土和250mm厚混凝土的复合衬砌结构,并采取相应的沉降控制措施,确保了施工安全和工程质量。
This paper introduced a engineering practice of cable tunnel passing through railway bridges. By Using the complex lining structure composed of grid-shotcrete and concrete and taking effective measures of settlement control, it was succeed to ensure the construction safety and engineering quality.
出处
《企业技术开发》
2009年第9期70-71,共2页
Technological Development of Enterprise
关键词
电缆隧道
复合衬砌结构
沉降控制
cable tunnel
complex lining structure
settlement control