介绍了邯钢新区2座顶底复吹转炉、2座双流板坯连铸机、双工位LF精炼炉、双工位RH精炼炉、铁水倒灌站、贴水预处理以及废钢间、公辅5大除尘系统、废钢间、炉渣间、公辅给回水、各种介质管道等的总体策划、安排及施工顺序,保证了工程均衡、有序、安全施工。
This article describe the main plan of Han-Gang new area ,arrangements and construction sequence of 2 top and bottom combined blown converter, 2double flow slab,twin LF, duplex RH top plant, iron pot stand down, pretreatment of hot metal and scrap house, 5 dedusting system of public auxiliary, scrap house ,slag house, recycled water of pubic auxiliary, all kinds of media piping in handan iron and sreel new area .It assured a balance, orderly and safety construction.