基于设备整体效能和多Agent的预测-反应式调度 被引量:3

Predictable-reactive scheduling based on overall equipment effectiveness and multi-agent
下载PDF
导出
摘要 生产过程中存在许多不确定性事件,其影响直接表现为生产效能方面的损失。为了减小这种影响,基于设备整体效能的角度,分析了不确定性事件对生产过程的干扰和对调度过程的影响,提出了一种基于设备整体效能的具有鲁棒性的预测调度实现方法,设计了一种基于多Agent协作机制的预测-反应式调度系统模型。仿真试验表明,该方法有助于提高调度系统抵御干扰生产的能力,增强反应式调度的应用效果。 A wide range of uncertainties would affect the Manufacturing process and resulted in product effectiveness lost directly. This paper discussed some issues related with executing production schedules in the presence of unforeseen disruptions on the shop floor, and presented a novel robust approach to solve the Predictable Scheduling Problem based on Overall Equipment Effectiveness(OEE). An agent-based framework used for Predictable-reactive Scheduling System was also proposed. Extensive numeric experiments had been conducted and the results had shown that the proposed approach was effective in absorbing the disruptions and solving a reactive scheduling problem.
出处 《计算机集成制造系统》 EI CSCD 北大核心 2009年第8期1599-1605,1613,共8页 Computer Integrated Manufacturing Systems
基金 国家自然科学基金资助项目(50475047 50375030) 广东省自然科学基金资助项目(05200197)~~
关键词 预测调度 反应式调度 鲁棒性调度 设备整体效能 多AGENT predictable scheduling reactive scheduling robust scheduling overall equipment effectiveness multi-agent
  • 相关文献

参考文献11

  • 1AYTUG H,LAWLEY M A,MCKAY K,et al.Executing production schedules in the face of uncertainties:a review and some future directions[J].European Journal of Operation Research,2005,161(1):86-110.
  • 2HERROELEN W,LEUS R.Project scheduling under uncertainty:Survey and research potentials[J].European Journal of Operation Research,2005,165(2):289-306.
  • 3SABUNCUOGLU L,BAYIZ M.Analysis of reactive scheduling problems in a job shop environment[J].European Journal of Operation Research,2000,125 (3):567-586.
  • 4VIEIRA G E,HERRMANN J W,LIN E.Rescheduling manufacturing systems:a framework of strategies,policies and methods[J].Journal of Scheduling,2003,6 (1):39-62.
  • 5LAGUNA M,LINO P,PEREZ Z,et al.Minimizing weighted tardiness of jobs with stochastic interruptions in parallel machines[J].European Journal of Operation Research,2000,127(2):444-457.
  • 6SLOWINSKI R.Scheduling under fuzziness[M].HAPKE M,eds.Heidelberg,Germany:Physica-Verlag,2000.
  • 7POLICELLA N.Scheduling with uncertainty-a proactive approach using partial order schedules[EB/OL].[2008-07-01].http://pst,istc.cnr.it/papers/policellAIcomm05,pdf.
  • 8KWON O.New methodology for measuring equipment performance and managerial effect in TPM[D].Seoul,Korea:PhD Thesis.Korea University,2005.
  • 9LEUS R,HERROELEN W.The complexity of machine scheduling for stability with a single disrupted job[J].Operations Research Letters,2005,33(2):151-156.
  • 10陈宇,陈新,陈新度,张平.制造企业生产设备运行维护实时管理系统[J].系统工程理论与实践,2008,28(4):65-72. 被引量:16

二级参考文献6

  • 1王军强,孙树栋,柴永生,司书宾.基于组件的设备管理信息系统的研究与实现[J].计算机集成制造系统,2004,10(9):1095-1099. 被引量:19
  • 2MESA International. “MES Explained: A High Level Vision” [Z]. White Paper6. Pittsburgh: Manufacturing Execution Systems Assoc, 2004.
  • 3Su K W, Hwang S L, Liu T T. Knowledge architecture and framework design for preventing human error in maintenance tasks[J]. Expert System with Application, 2000(19) :219- 228.
  • 4Willmont P. Total Productive Maintenance-The Western Way[ M ]. Great Britain: Butterworth Heinemann Ltd, 1994, 32- 37.
  • 5Pintelon L, Wassenhove L V. A maintenance management tool[J]. International Journal of Management Science, 2002, (18) : 59 - 70.
  • 6Ivancic I. The development of maintenance in modem production [ C].Dubrovnik, Croatia: Conference Proceedings, Euromaintenance.2001, 17 - 35.

共引文献15

同被引文献22

  • 1金宏,王宏安,傅勇,王强,王晖.模糊反馈控制实时调度算法[J].软件学报,2004,15(6):791-798. 被引量:13
  • 2陶海军,王亚东,郭茂祖,王翰伦.基于熟人联盟及扩充合同网协议的多智能体协商模型[J].计算机研究与发展,2006,43(7):1155-1160. 被引量:20
  • 3徐刚,于泳波.基于改进的粒子群算法求解0/1背包问题[J].齐齐哈尔大学学报(自然科学版),2007,23(1):71-74. 被引量:3
  • 4NIU Gang-gang,SUN Shu-dong,LAFON P,et al.A predictive-reactive approach for JSP with uncertain processing times[C]//Proc of IDMME.2010:1-4.
  • 5YANG Bi-bo,GEUNES J.Predictive-reactive scheduling on a single resource with uncertain future jobs[J].European Journal of Operational Research,2008,189(3):1267-1283.
  • 6PETROVIC D,DUENAS A.A fuzzy logic based production scheduling/rescheduling in the presence of uncertain disruptions[J].Fuzzy Sets and Systems,2006,157(16):2273-2285.
  • 7DUENAS A,PETROVIC D.An approach to predictive-reactive scheduling of parallel machines subject to disruptions[J].Annals of Operations Research,2008,159(1):65-82.
  • 8PETROVIC S,PETROVIC D,BURKE E.Fuzzy logic-based production scheduling and rescheduling in the presence of uncertainty[J].Planning Production and Inventories in the Extended Enterprise,2011,152(6):531-562.
  • 9SAKAWA M,MORI T.An efficient genetic algorithm for job-shop scheduling problems with fuzzy processing time and fuzzy due date[J].Computers & Industrial Engineering,1999,36(2):325-341.
  • 10MICHALEWICZ Z.Genetic algorithms+data structures=evolution programs[M].3rd ed.New York:Springer,1994.

引证文献3

二级引证文献3

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部