摘要
引红济石调水工程属省内的跨流域调水工程,输水隧洞长近20 km,工程采用钻爆法与TBM联合施工方案,工程区地质条件极为复杂,突发性涌水、地质断裂带、长距离隧洞排水、通风、出渣等问题对采用TBM施工提出了特殊要求。应尽早对引红济石工程施工要求的TBM设备进行研究,为设备采购、制造作好前期技术支持。
The water diversion project from Hongyan to Stone river project in Shaanxi Province is the inter-basin water transfer project, water conveyance tunnel length of about 20 km, the use of drilling and blasting method works + TBM joint implementation plan. The project area has extremely complicated geological conditions, sudden gushing water, geological fault crack band, long-distance tunnel drainage, ventilation, transportation and other issues raised on the use of TBM construction of a special request. The research of TBM equipment should be started as soon as possible, in order to offer technical support for equipment procurement, manufacturing.
出处
《杨凌职业技术学院学报》
2009年第3期7-9,共3页
Journal of Yangling Vocational & Technical College
关键词
TBM
施工
适应性
初探
TBM
constructions adaptation
preliminary study