摘要
针对逆作法设计与施工中关键技术进行研究。对逆作条件下作为主体结构承重墙的地下连续墙的设计与施工,地下连续墙与地下结构内部梁板等构件中的可靠连接进行仔细地探讨。
The key techniques of TDCM on design and construction were studied in this paper. On diaphragm walls that were used as a part of main structures, some designs and constructions, and reliable joint structures between diaphragm wall and basement beam or plate were extensive analyzed.
出处
《应用能源技术》
2009年第9期7-9,共3页
Applied Energy Technology
关键词
地下连续墙
关键技术
施工
Diaphragm wail
Key techniques
Construction