预浸水法在棉山湾水库湿陷性黄土坝基处理中的应用

The application of presoaking methods in treatment for collapsible loess ground soil at Mianshanwan reservoir
下载PDF
导出
摘要 在湿陷性黄土地基上修建土坝,由于地基湿陷引起附加沉降对土坝带来很大隐患,因此,选择适宜的地基处理方法成为建坝的关键.以棉山湾水库左岸Ⅳ级自重湿陷性黄土坝基采用预浸水法处理为例,介绍了预浸水处理的具体方法,通过观测成果、浸水效果分析,探求湿陷量、耗水量与浸水时间的关系及湿陷量的阶段特征.棉山湾水库湿陷性黄土坝基预浸水处理的成功应用,为宁夏山区湿陷性黄土基础上建坝提供了详实的资料和经验,为类似工程起到借鉴作用. If dam is built on collapsible loess ground soil, great hidden troubles might be caused by the additional settlement of the collapse of loess ground soil, so the key point to build dam is to use proper treatment for ground settlement. Take the presoaking methods in treatment for building dam on IV level self-weight collapsible loess ground soil on the left bank of Mianshanwan reservoir as an example. This article introduces presoaking methods in treatment for dam building at collapsible loess ground soil. Based on surveying the effectiveness, analyzing presoaking efficiency, measuring the collapsibility, water- consuming, soaking time and the phase characteristics, the application of the presoaking methods is effective. This successful attempt not only provides concrete data, information and experience for future dam building on collapsible loess ground soil in Ningxia, but also provides guidance for similar projects.
出处 《宁夏工程技术》 CAS 2009年第3期253-255,259,共4页 Ningxia Engineering Technology
关键词 湿陷性黄土 预浸水法 观测成果 浸水效果 collapsible loess ground soil effectiveness survey presoaking method presoaking effectiveness analysis
  • 相关文献

参考文献5

  • 1顾淦臣,陈明致,郭城谦,等.土坝设计(下册)[M].北京:水利电力出版社,1978.
  • 2宁夏水利水电勘测设计院地质队.宁夏海原县棉山湾水库工程地质勘察报告[R].银川:宁夏水利水电勘测设计院地质队,2001.
  • 3陕西省建筑科学研究设计院.CBJ25-90.湿陷性黄土地区建筑规范[S].北京:中国计划出版社,1990.
  • 4陕西省建筑科学研究设计院.GB50025-2004.湿陷性黄土地区建筑规范[S].北京:中国建筑工业出版社,2004.
  • 5宁夏水利水电勘测设计院地质队.宁夏海原县棉山湾水库坝址左岸预浸水处理场地补充工程地质勘察报告[R].银川:宁夏水利水电勘测设计院地质队,2003.

共引文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部