摘要
亭子口水利枢纽施工工期紧,坝址两岸施工场地狭窄,施工导流程序复杂。根据因地制宜、节约用地、场地安全和环境保护的枢纽施工总布置原则,对场内外交通、料场开采及运输、渣场、施工场地、施工设施和防洪排水进行了规划设计。施工总体布置格局较好地体现了当前的施工管理模式和生产力水平。
There are special characteristics of tight construction sehedule, narrow construction area in two banks of dam site and eomplieated diversion for Tingzikou Project. According to the general layout principles of adapted to local eonditions, economical use of land, site safety and environmental protection, the planning and design for inside and outside toad, aggregate mining and transportation, residue field, construction site, construetion facilities and flood prevention and drainage are earried out. The overall layout of construction is better to reflect the current level of construction management and productivity.
出处
《水力发电》
北大核心
2009年第10期8-10,47,共4页
Water Power
关键词
场地规划
施工道路
防洪排水
渣场防护
亭子口水利枢纽
site planning
construction of roads
flood prevention and drainage
residue field protection
Tingzikou Water Control Project